Default How do you get a ground rod to 6 feet ?


The minimum depth is provided by the building code. Since the footer
must be below the frost line the resultant Ufer Ground is also below the
frost line. If it's not it will be ineffective.



To split hairs a bit, you can build a Ufer ground that isn't a
structural footer, and so, may not be subject to the frost line rules.