Tower project - Phase 2 Complete
Allodoxaphobia wrote:
On Sat, 07 Mar 2009 15:03:33 -0600, MTV wrote:
Phase 2 was first digging the 36' x 36" x 45" hole for the base, then
securing the tower rod base and pouring the concrete.
A 36 foot deep hole ought to hold up a freestanding 100' tower --
or more! :-)
It's actually 52" deep; the tower mfgr said min. of 45"; ARRL handbook
says 6' but only 30" sq, depending on the type of soil.
Marv
|