| Home |
| Search |
| Today's Posts |
|
|
|
#1
|
|||
|
|||
|
On Apr 2, 8:07 am, Roger wrote:
Ahhh...The water pipe must be bonded to the electrical system, but the main ground must be at the entrance. Here, we have plastic water pipe all the way to the main from the meter, yet we have to bond the meters which are metal with plastic running in and plastic running out. ... It's really easy to avoid here. We do not have metal piping available for grounding. Roger Halstead (K8RI & ARRL life member) (N833R, S# CD-2 Worlds oldest Debonair)www.rogerhalstead.com Roger is correct here. Underground water pipe electrode is no longer sufficient as the earth ground in most locations for a long list of reasons. Yes, that water pipe must be bonded to the AC electric so that plumbing is electrically same voltages as everything else inside the house - human safety. Public utility water system may have voltages different from AC electric if the two are not bonded - as has been observed when a fault was created outside the building. Destructive currents entering on that water system must be eliminated by being bonded to AC electric. Many other reasons why AC breaker box must be bonded to the cold water pipe. Yes cold water pipe may act as an earthing electrode. But it is no longer sufficient as the earthing electrode. An earthing electrode - one that all utilities must use - is not the water pipe. All utilities must connect to a separate and dedicated earthing electrode defined by code (as defined in Article 250.52 A - paragraphs 2 through 7). The code defines 7 types of earthing electrodes. The only electrode not sufficient is cold water pipe - paragraph 1. For lightning, an antenna (or satellite dish) is typically treated as if a separate structure as demonstrated in this application note: http://www.erico.com/public/library/...es/tncr002.pdf Antenna wire must connect to the same building 'single point' earthing electrode. IOW any wire in any cable going to the station must first connect to that single point earthing electrode (either by hardwire or protector) before entering the building. Best is to have the antenna earthing also connected, by underground wire, to that same single point ground. This for lightning protection is beyond what is called for by National Electrical Code for numerous reasons. First, NEC only addresses human safety. The OP is asking about transistor safety. Second, the code does little to address impedance. Grounding for human safety is mostly about resistance - not impedance. Third, any grounding system dependent on some other trade (ie plumber) is no longer considered safe or sufficient. A ground system must meet NEC requirements. Then it must exceed those requirements. For lightning protection, a cold water pipe is not longer considered a good solution because that earthing electrode is just not sufficient. Also better is to earth lightning rods and antennas before that ground wire connects to a building's single point ground. Notice the underground wire connection between antenna earth ground and building earth ground. And finally a purpose of earthing that is beyond what the NEC requires. A station needs earthing that provided both equipotential and conductivity. Code concentrates on conductivity. But for equipotential, we do things beyond what is normally sufficient for human safety. We install Ufer grounds or halo grounds that completely surround the protected facility. We relocate all utilities so that each wire in each cable makes a 'less than 10 foot' connection to that common earth electrode. Any exception to the single point earth ground (as defined in code) is not permitted when also earthing for transistor safety. Route earthing wires to be separate from all other wires, no splices, no sharp bends, not inside metallic conduit, etc. All earthing wires remain electrically separate until all meet at the single point ground. Conditions beyond what code demands or permits. Consider with care information in that figure in: http://www.erico.com/public/library/...es/tncr002.pdf Things recommended are not immediately obvious. Reasons for this involve both equipotential and conductivity. Both are required for station protection. |
|
#2
|
|||
|
|||
|
w_tom wrote:
On Apr 2, 8:07 am, Roger wrote: Ahhh...The water pipe must be bonded to the electrical system, but the main ground must be at the entrance. Here, we have plastic water pipe all the way to the main from the meter, yet we have to bond the meters which are metal with plastic running in and plastic running out. ... It's really easy to avoid here. We do not have metal piping available for grounding. Roger Halstead (K8RI & ARRL life member) (N833R, S# CD-2 Worlds oldest Debonair)www.rogerhalstead.com Roger is correct here. Underground water pipe electrode is no longer sufficient as the earth ground in most locations for a long list of reasons. As Thomas said, Roger is correct if the underground water service pipe is plastic. Missing is any of the “long list of reasons”. Many other reasons why AC breaker box must be bonded to the cold water pipe. Yes cold water pipe may act as an earthing electrode. But it is no longer sufficient as the earthing electrode. An earthing electrode - one that all utilities must use - is not the water pipe. All utilities must connect to a separate and dedicated earthing electrode defined by code (as defined in Article 250.52 A - paragraphs 2 through 7). The code defines 7 types of earthing electrodes. The only electrode not sufficient is cold water pipe - paragraph 1. The code says (250.50) all electrodes listed in 250.52-A-1 through 6 MUST (where present) be connected together to form the earth electrode system. 250.52–A-1, which is conveniently missing from w_’s list, is metal underground water pipe (at least 10 feet metal underground). ONLY if the pipe is not 10 feet long underground is bonding used instead. Water pipe requires a “supplemental” electrode. That is because the metal pipe may in the future be replaced by plastic. From the National Electrical Code Handbook - same publisher as the NEC “The requirement to supplement the metal water pipe is based on the practice of using plastic pipe for replacement when the original metal water pipe fails. This leaves the system without a grounding electrode unless a supplementary electrode is provided.” Requiring a supplemental electrode does not indicate there is any defect in metal pipe as an electrode. As Thomas indicates, it is likely by far the best electrode available in urban areas with metal supply. Earthing connection of other services, like the phone NID, may be made to the water pipe within 5 feet of the entrance to the building (the connection of the power earthing conductor is in the same 5 foot span). We install Ufer grounds or halo grounds that completely surround the protected facility. From http://www.lightningsafety.com/nlsi_...finitions.html “Halo Grounded Ring: A grounded No. 2 wire, installed around all four walls inside a small building, at an elevation of approx. six inches below the ceiling. There are drops installed from the halo to the equipment cabinets and to waveguide ports, interior cable trays etc. Halo rings serve as connector points to achieve ground references of interior metallic objects. These, in turn, are connected to the main ground bus bar.” Perhaps you mean “ground ring”? ---------------- The code now requires a Ufer electrode in new construction with concrete foundations or footings. -- bud-- |
| Reply |
| Thread Tools | Search this Thread |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Forum | |||
| Yacht Rf ground and radials | Antenna | |||
| Safety ground versus RF ground for a 2nd Floor shack | Antenna | |||
| Grounding A Radio ? | Shortwave | |||
| Lightning and Grounding | Antenna | |||
| lightning protection | Shortwave | |||